Week 13. ( Lots of work so will be several posts... ) setting in the roof frames, painting them. Local women lime washing the adobe bricks. Attaching the roof battens. removing formwork.
Week 8. Getting over the torrential rain from week 7, and the devestation caused to the footings, we begin ramming! Mixing clay, sand and gravel to form the wall. Making bricks with Ratty. #checkcheck
Week 3. Filling the foundations and building the footings. A presentation to the village of the project and Jennie’s thesis project followed by lots of dancing.
Raumgeschichten Workshop, Ghana, Supported by the NKA Foundation.
Jennie took part in this amazing workshop, which is what inspired her to apply for the 2018 DESIGN-BUILD CHALLENGE IN GAMBIA set up the Stamping Ground Workshop